You have recently taken over a new project when the previous project manager resigneD、While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, you should recommend ______ .

A、issuing budget updates
B、revising the cost baseline
C、corrective action e. g. adjusting schedule activity budgets
D、closing the project
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

13%的考友选择了A选项

84%的考友选择了B选项

2%的考友选择了C选项

1%的考友选择了D选项