【单选题】

During the sixth monthly update on a ten-month, $30,000 project, the analysis shows that the cumulative PV is $20,000, the cumulativeAC、is $10,000, and the cumulativeEV is $15,000. In planning its action, management can conclude all of the following from these figuresEXCEPT:

A、Less has been accomplished than was planneD、
B、Less has been spent than planneD、
C、Continuing performance at the same efficiency with no management intervention, the project will probably be completed ahead of schedule and over budget.
D、Continuing performance at the same efficiency with no management intervention, the project will probably be completed behind schedule and under budget.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

10%的考友选择了A选项

7%的考友选择了B选项

82%的考友选择了C选项

1%的考友选择了D选项