You are a project manager of a small construction project. Your project was budgeted for US $72,000 over a six week perioD、As of today, you’ve spent US $22,000 of your budget to complete work that you originality espected would cost US $24,000.According to your schedule, you should have spent US $30,000 by this point.Based on these circumstances, you project could beBEST described as ______ .
A、under budget B、over budget C、on budget D、need more info