The estimate at completionEAC、is the projected or anticipated total final value for a schedule activity, WBS component, or project when the defined work of the project is complete
D、To determine theEAC, assuming no management intervention, which of the following information is needed A、The earned valueEV)and the actual cost to dateAC、. B、The cost performance indexCPI)and the cost varianceCV). C、The actual cost to dateAC、and the cost performance indexCPI). D、The actual cost to dateAC、and the estimate to completeETC、.