You have recently taken over a new project when the previous project manager resigneD、While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, you should recommend ______ .
A、issuing budget updates B.revising the cost baseline C.corrective action adjusting schedule activity budgets D.closing the project