As a project manager, you are aware that estimating schedule activity costs involves developing an approximation of the costs of the resources needed to complete each schedule activity. In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including risks.Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution and product operations. The cost estimating process considers whether the expected savings can offset the cost of additional design work.Cost estimates are generally expressed in units of currency to facilitate comparisons both within and across projects.Cost estimates can also benefit from refinement during the course of the project to reflect on the additional detail available. For your project, which is in the initial phases, your team suggested a rough order of magnitude estimate—this could be in the range of ______ .

A、-75% to+125%
B.-50% to+100%
C.-25% to+50%
D.None of the above
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

31%的考友选择了A选项

68%的考友选择了B选项

0%的考友选择了C选项

1%的考友选择了D选项

你可能感兴趣的试题

YourecentlywereassignedtoaprojectinAustrYourcompanyisgoingtostartanenvironmentde实验设计可以帮助降低产品性能对环境变化或其他变化的敏感性,使产品性能更加稳定。尽ProjectteamAhasbeenhiredtomanageatranspoYouaretheprojectmanagerofaprojectwhichwo在你负责的项目上,管理层已经签发了项目章程,你正在组织项目管理团队成员编制项目范