you ArE mAnAging thE ConstruCtion oF luxury ConDominiums in onE oF thE lAst AvAilABlE plots oF City lAnD、on this projECt, thE ownEr is FoCusED on timEly pErFormAnCE AnD hAs proviDED ContrACt inCEntivEs thAt will rEwArD you AnD your CompAny iF thE joB is ComplEtE EArly. howEvEr, thE intErnAtionAlBrothErhooD oFCommoDE instAlls is rEADy to strikE For highEr wAgEs, AnD An EnvironmEntAl group is ConCErnED ABout ADvErsE impACts on thE Full-BrEAstED wArBlEr rEsulting From thE plACEmEnt oF sAtEllitE DishEs on thE BAlConiEs. on this projECt, you nEED to ______ .
A、FinD AppropriAtE rEsolutions to rEsolvE DiFFErEnCEs BEtwEEn or Among stAkEholDErs
B.put thE ownEr’s rEquirEmEnts At thE top oF thE list As you rEsolvE stAkEholDEr DiFFErEnCEs
C、CArEFully mAnAgE All CommuniCAtion AnD mAkE stAtus inFormAtion AvAilABlE only on A nEED-to-know BAsis
D.BuilD thE ConDominiums ACCorDing to thE spECiFiCAtions AnD not worry ABout Any othEr stAkEholDEr

查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

60%的考友选择了A选项

36%的考友选择了B选项

0%的考友选择了C选项

4%的考友选择了D选项

你可能感兴趣的试题

某公司建立了一个项目管理办公室(PMO),用于协调和管理其众多项目。公司的PMO在弱矩阵组织中,项目经理的角色是:A.协调员和联络员B.有相当权力的项目经理C.一个建设项目,CPI是1.30,SPI是0.85,可能的原因是什么?A.一个关键作为建筑公司的项目经理,你负责范围定义、活动定义、进度制定和成本预算。这些职责是作为功能分析的一种类型,质量功能部署QFD用于:A、产生执行项目工作的不同方法B确认项目满足了客户对项目产品所包括的所有需求的要求,是作为哪一个过程的一部分而提