试题查看

首页 > PMP考试 > 试题查看
【单选题】

You are the project manager in an automobile manufacturing company.Because of heavy rains,the machine parts required in your manufacturing process which a vendor was sending to you,could not reach you in time.You had anticipated this risk and planned for it in your risk response plan.So,as part of your risk response plan,you started using machine parts which had been supplied 1 year ago and were not utilized at that time.However,this has subjected your project to a new risk-that the machine parts which were not used for 1 year might be a having higher level of defects.This new risk can also be called______.

A、unidentifiable risk
B.unmanageable risk
C.secondary risk
D.residual risk
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

4%的考友选择了A选项

22%的考友选择了B选项

65%的考友选择了C选项

9%的考友选择了D选项

你可能感兴趣的试题

挣值管理整合了以下哪些要素?()A.范围、时间和成本B时间、成本和质量C.风险、控制成本过程的输出包括()。A.成本概算B成本预算C成本基准D成本预测制定预算过程的主要输入包括()。A.范围基准、风险登记册、人力资源计划和组织过程下列哪项不?估算成本过程的输入?()A.工作分解结构、项目进度计划B人力资源计划机会成本是()。A.开展一个新项目而必须付出的代价B.为做一件事而放弃做另外一件可以利用相关变量之间的历史关系进行()。A.参数估算B类比估算C.自下而上估算D