You are working as a project manager for a major US-based public company.This morning you received alarming news that the major strategic project you are responsible for will not be able to provide financial benefits to the organization as expecteD、This drawback will significantly influence future profits of the entire corporation.What should you do right now

A、You should not overact and check at least three options before making any decision
B.You must immediately inform the corporate management to ensure real time issuers disclosure
C.You should investigate detailed information on the problem before escalating it to corporate managemen
D.You should find a quick solution for the problem and implement this immediatel
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

82%的考友选择了B选项

2%的考友选择了C选项

14%的考友选择了D选项