You are running a project for a customer based on a cost reimbursable contract with the following terms:Target costs,$1000000;fix fee,100000;benefit/cost sharing,80/20;price ceiling,1200000.Which is the PT
A、(point of total assumption,break point)of the project A、$1300000. B.$1500000. C.$80000. D.$1125000.