【单选题】

You are the project manager for software development project.The feasibility study can start any time and takes 1 week and requirement gathering takes 2 weeks which can start only after feasibility study.The design and test plan development can start in parallel after the requirements gathering.Test plan preparation takes 8 weeks followed by a review by the customer and the time estimated for review is 1 week.After the review,Test data preparation takes 6 weeks.Design takes 6 weeks and it is followed by development and unit testing,for one module it takes 2 weeks and for the other module it takes 2 weeks.There are no dependencies between modules and they can be developed simultaneously.After test data preparation and development and unit testing of both the modules,there is 2 weeks system testing.What is duration of the critical path

A、14 week
B.15 week
C.20 week
D.19 week
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

19%的考友选择了A选项

26%的考友选择了B选项

54%的考友选择了C选项

1%的考友选择了D选项

你可能感兴趣的试题

以下哪一项目描述了小组内的部的强大压力,使得团队不行不放弃重要的、有创造性的主意你负责的项目已经进行了18个月了。某天,公司的CEO给你发了一封电子邮件,要你向现在的项目比以往的项目牵扯到更多的国际合作和形形色色的干系人。因此,如果没有在项现在的项目比以往的项目牵扯到更多的国际合作和形形色色的干系人。因此,如果没有在项币值波动、政治动荡、中央和地方政府之间的竞争,以及不同利益集团之间的冲突可能会干你目前正忙着做项目的收尾工作。在这个令人兴奋的最后阶段,在下列哪个方面最容易引发