The software development project is not going well.There are over 30 stakeholders,and no one can agree on the project objectives.One stakeholder believes the project can achieve a 30 percent improvement while another believes a 50 percent improvement is possible.The project manager thinks a 10 percent improvement is more realistiC、What is theBEST course of action

A、Move forward with the project and look for more information later to settle the issu
B.Average the numbers and use that as an objectiv
C.Perform a feasibility analysi
D.Ask the sponsor to make the final decisio