【单选题】

During execution of a project which is performed for a customer on a T & M (time and material)contract base,a new project manager is taking over the assignment.He discovers that two members assigned to the project have charged time without performing any work for the project customer.Upon further investigation,he determines that this occurred because there have been no other project assignments open for these employees.The customer is unaware of these facts.Which of the following should he do

A、Try to find some productive work for these staff members in the project and leave them on the tea
B.The best thing is to do nothinThe customer will not realize the problem anywa
C.Try to find a responsible person for the over-assignment who can be made accountabl
D.Take the two people off the team immediately and arrange for the refund of the excess charges to the custome
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

如答案有误或试题有侵权,请联系我们。[提交反馈][在线客服]

根据网考网移动考试中心的统计,该试题:

19%的考友选择了A选项

15%的考友选择了B选项

16%的考友选择了C选项

50%的考友选择了D选项

你可能感兴趣的试题

你刚刚得知一位团队成员已经给项目增加了一项很小的额外功能。假设增加这个额外功能不项目管理办公室(PMO)的主要职能通常包括以下几个方面,除了()。A.控制分配给YouaretheprojectmanagerofalargesoftwaredYouareaprojectmanagertoupgradethecomputeYouareworkingonaprojectforBrightIdeaInc.Youhavetofinishaprojectwithin2weeksandyo
版权所有网考网(netkao.com)All Rights Reserved

警告:系统检测到您的账号存在安全风险

抱歉,您的账号因涉嫌违反网考网购买须知被冻结。您可在“网考网” 微信公众号中的“官网服务”- "账号解封申请”申请解封。

微信扫描关注网考网