【单选题】

A、project manager spent some days to create a multi-page document which he called project charter.The document should have been issued by the project sponsor.The sponsor found the document outsized and asked for a condensed document.Which of the following is not normally an element of the project charter

A、The formal authorization to apply organizational resources to project activitie

B.Detailed control account and work package description

C.The business need that the project was undertaken to addres

D.The product description or a reference to this documen

查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

14%的考友选择了A选项

83%的考友选择了B选项

2%的考友选择了C选项

1%的考友选择了D选项