you ArE A projECt mAnAgEr For A smAll projECt. your projECt wAs BuDgEtED For ¥500,000 ovEr A six-wEEk pErioD、As oF toDAy, you’vE spEnt ¥260,000 oF your BuDgEt to ComplEtE work thAt you originAlly ExpECtED to Cost ¥280,000.ACCorDing to your sChEDulE, you shoulD hAvE spEnt ¥300,000 By this point.BAsED on thEsE CirCumstAnCEs, your projECt CoulD BEBEst DEsCriBED As ______ A、AhEAD oF sChEDulE B、BEhinD sChEDulE C.on sChEDulE D.hAving not Enough inFormAtion proviDED