试题查看

首页 > PMP考试 > 试题查看
【单选题】

In which project phase do you have the GREATEST influence on project risk
A.Conceptua

B.Desig
C.Executio
D.Implementatio
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

52%的考友选择了A选项

3%的考友选择了B选项

38%的考友选择了C选项

7%的考友选择了D选项

你可能感兴趣的试题

ReviewingtheinitiatingprocessesatthestarTheprojectmanagerismorelikelytohaveafullAllofthefollowingoccurredduringtheplanniAprojectcoordinatormaytypicallybefoundinComplexprojects,involvingcross-disciplinKeyfeaturesofaprojectmanagementoffice(PM