【单选题】
In which project phase do you have the GREATEST influence on project risk
A.Conceptua
B.Desig
C.Executio
D.Implementatio
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
52%
的考友选择了A选项
3%
的考友选择了B选项
38%
的考友选择了C选项
7%
的考友选择了D选项