【单选题】

Which of the following is true about the WBS:
A.The WBS is another term for the Gantt char

B.Each descending level of the WBS represents an increasingly detailed definition of the project wor
C.Work not in the WBS is usually defined in the scope statement of the projec
D.The WBS shows only the critical path activitie
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

15%的考友选择了A选项

83%的考友选择了B选项

0%的考友选择了C选项

2%的考友选择了D选项