As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for ______ .
A.estimating future projects

B.changing the project scope
C.defining future project tasks
D.validating the quality process
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

18%的考友选择了A选项

18%的考友选择了B选项

7%的考友选择了C选项

57%的考友选择了D选项