【单选题】

You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project
A.Project selection method

B.Additional plannin
C.Corrective actio
D.Project management information syste
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

14%的考友选择了A选项

13%的考友选择了B选项

4%的考友选择了C选项

69%的考友选择了D选项