A project has the following earned value data assessed:AC=$4000000;CV=$-500000;SPI=1.12;BAC=$9650000.What is the earned value of the project
A.$3000000.
B.$3500000.
C.$4480000.
D.$5650000.
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
9%
的考友选择了A选项
85%
的考友选择了B选项
0%
的考友选择了C选项
6%
的考友选择了D选项