The close project process is a part of which of the following project management knowledge areas
A.project scope managemen

B.project integration managemen
C.project time managemen
D.project communication managemen
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

89%的考友选择了B选项

7%的考友选择了C选项

2%的考友选择了D选项