【单选题】

When the project cost is $2000 and the profit is $500,what is the BCR for the project
A.2500.

B.25%.
C.4.
D.not enough information to calculate BC
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

7%的考友选择了A选项

2%的考友选择了B选项

2%的考友选择了C选项

89%的考友选择了D选项