In your project,you want to monitor and control project processes associated with initiating,planning,executing and closing.This will help you take corrective or preventive action to control project performance.In this context,what should you do first
A.Review all project forecast

B.Detail all the activities of project team members involved in executing administrative closure for the projec
C.Review the project management plan and work performance information for your projec
D.Manage project risk
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

3%的考友选择了A选项

13%的考友选择了B选项

65%的考友选择了C选项

19%的考友选择了D选项