【单选题】

You are the project manager of Alpha Network Inc.Your company is doing network planning for a major bank.You are planning to digram the activity dependancies using activity list.Which of the following is true
A.PDM is also the AOA diagramming metho

B.PDM is also the AOD digramming metho
C.PDM is also AON digramming metho
D.PDM is also ADM diagramming metho
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

4%的考友选择了A选项

18%的考友选择了B选项

60%的考友选择了C选项

18%的考友选择了D选项