试题查看

首页 > PMP考试 > 试题查看
【单选题】

You do not expect the types of variances that have occurred on the project to date to continue.If BAC=300,ETC=275,PV=300,AC=200,EV=250,and CPI=1.25,what is the EAC
A.240.

B.250.
C.475.
D.150.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

4%的考友选择了A选项

74%的考友选择了B选项

8%的考友选择了C选项

14%的考友选择了D选项

你可能感兴趣的试题

SinceyourqualityprocesswasnotuptothefourWhichtypeofwarrantyisenactedifaserviceorInwhichphaseoftheprojectlifecycle,arecosBeingtheprojectmanagerinasoftwareprojectHowshouldchangemanagementbeplannedforA.CUnderstandingof______characteristicsofpe