You do not expect the types of variances that have occurred on the project to date to continue.If BAC=300,ETC=275,PV=300,AC=200,EV=250,and CPI=1.25,what is the EAC
A.240.
B.250.
C.475.
D.150.
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
4%
的考友选择了A选项
74%
的考友选择了B选项
8%
的考友选择了C选项
14%
的考友选择了D选项