【单选题】

When a project manager is engaged in negotiations,non-verbal communication skills are of______.
A.little importance

B.major importance
C.importance only when cost and schedule objectives are involved
D.importance only to ensure you win the negotiation
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...