About midway through the project,the project manager learns that most members of the project team do not review the weekly project updates.What should the project manager do
A.Great a signature log do team members can indicate when they have read the report

B.Revise the communications plan appropriately to meet the information needs of the stakeholder
C.Improve the layout of the weekly project updates to encourage reading by team member
D.Go to the team members first hand to inquire why they are not reading the report