The organization of the project is very important for successful implementation. Which factor does not have an impact of design of the project organization
A.Environmental force
B.Schedule limitation
C.Strategic choice
D.Technological factor
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
43%
的考友选择了A选项
54%
的考友选择了B选项
1%
的考友选择了C选项
2%
的考友选择了D选项