【单选题】
Inaprojectplan,whentheprojectmanagerschedulesactivities,he(orshe)oftenuses()method,precedencerelationshipsbetweenactivitiesarerepresentedbycarelessconnectedbyoneormorearrows.Thelengthofthearrowrepresentsthedurationoftherelevantactivity
A.causalitydiagram.
B.Ganttchart
C.histogram
D.arrowdiagram