【单选题】
A project schedule completion date will change if ______ .
A.the critical path is reduced
B.the contingency is no longer available
C.no float time is available
D.project resources are reduced
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
74%的考友选择了A选项
11%的考友选择了B选项
3%的考友选择了C选项
12%的考友选择了D选项