All of the following are true about resource leveling EXCEPT: A.Can be used to keep selected resource usage at a constant level during specific time period
B.Often results in a projected duration for the project that is longer than the preliminary project schedul C.Is sometimes called the resource-based metho D.Is used to develop a meaningful WB