【单选题】
Analogous duration estimating is ______ .
A.bottom-up estimating
B.frequently used to estimate project duration when there is a limited amount of detailed information
C.similar to multiple duration estimating
D.deductive estimating
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
27%
的考友选择了A选项
69%
的考友选择了B选项
2%
的考友选择了C选项
2%
的考友选择了D选项