试题查看

【单选题】

Analogous duration estimating is ______ .
A.bottom-up estimating

B.frequently used to estimate project duration when there is a limited amount of detailed information
C.similar to multiple duration estimating
D.deductive estimating
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

27%的考友选择了A选项

69%的考友选择了B选项

2%的考友选择了C选项

2%的考友选择了D选项

你可能感兴趣的试题

TheprojecttimemanagementprocessesincludeThehybridofaprojectnetworkdiagramandbarcAnactivityhasanoptimisticestimateof10dayInyourproject,yourealizetheimportanceofdAllthefollowingarebenefitsoffasttrackingInyourproject,youareintheprocessofcreati