【单选题】

Tools and techniques to acquire the project team include all of the following EXCEPT ______ .
A.pre-assignment

B.acquisition
C.staffing management plan
D.negotiation
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

5%的考友选择了A选项

27%的考友选择了B选项

64%的考友选择了C选项

4%的考友选择了D选项