You are aware that an employee in your project may potentially get a promotion—however, there is a possibility that he may get transferred after his promotion, thus impacting your project. In this situation, you should:
A.Give a bad recommendation about the person so as to delay the promotion of the person until project is ove

B.Inform the employee about the potential promotion, and ask him to transition his responsibilities to another perso
C.After the employee gets the promotion and is told of the transfer, you ask him to prepare a transition pla
D.Hire another resource who can replace the person after he gets the promotio
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

20%的考友选择了B选项

79%的考友选择了C选项

1%的考友选择了D选项