【单选题】

As a project manager, you are in the process of creating a listing of all the project team members, their roles and communication information. This information should reside in the ______ (choose the best answer).
A.project plan

B.project team directory
C.performance reports
D.responsibility assignment matrix
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

11%的考友选择了A选项

68%的考友选择了B选项

7%的考友选择了C选项

14%的考友选择了D选项