when a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on
budget. a. reduce features and/or functionality b. increase risk. c. incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times) d. all of the above. e. a and b only