【单选题】Of the following estimates, which most accurately reflect the actual cost of the project
- A) Conceptual estimates.
- B) Order of magnitude estimates.
- C) Preliminary estimates.
- D) Bottom-up estimate.
【单选题】Of the following estimates, which most accurately reflect the actual cost of the project