根据网考网考试中心的统计分析,以下试题在2018/10/31日PMP考试习题练习中,答错率较高,为:49%
【单选题】ixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:
a. buyer
b. third party
c. contractor
d. all of the above
e. none of the above
网考网参考答案:C,答错率:49%
网考网试题解析:
暂时没有解析查看试题解析出处>>