根据网考网考试中心的统计分析,以下试题在2018/12/11日PMP考试习题练习中,答错率较高,为:33%
【单选题】The WBS is:
A An organization oriented family tree of the project.
B A task oriented family tree of the project.
C A cost centered structure of the project.
D Only required on large complex projects where separately identifiable work packages are
difficult to construct.
E None of the above
网考网参考答案:B,答错率:33%
网考网试题解析:
暂时没有解析查看试题解析出处>>