【单选题】During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B Is still the original baseline but annotated to reflect that a change has taken place.
C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E Is the same since baseline schedules cannot change once the development phase is completed.
网考网参考答案:C,答错率:80%