试题查看

首页 > PMP考试 > 试题查看
【单选题】

 A program can best be described as: 

A A grouping of related activities which last two years or more 
B The first major subdivision of a project 
C A grouping of projects, similar in nature, which support a product or product line and 
have no definable end point 
D A product line 
E Another name for a project 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

75%的考友答对了

你可能感兴趣的试题