试题查看

首页 > PMP考试 > 试题查看
【单选题】

A project manager believes that modifying the scope of the project may provide added value 

for the customer. The project manager should: 
A Change the scope baseline 
B Prepare a variance report 
C Call a meeting of the configuration control board 
D Change the project’s objectives 
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

67%的考友答对了

你可能感兴趣的试题

The"rollingwave"or"movingwindow"conceptiInterfacingwiththecustomerafterprojectgoUsingtheWBSshownintheSpecialwindow,atypiInpreparingagoodprojectdefinition,experiProjectlifecyclesprovideabettermeansofmeThecontractualstatementofwork(CSOW)AMust