【单选题】

The contractual statement of work (CSOW) 

A Must be the same as the proposal statement of work 
B Does not identify reporting requirements 
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work 
D Identifies the contractor’s organizational structure for the project 
E All of the above