【单选题】

Including the customer in the process of project planning is: 

A Slow and counterproductive. 
B Essential in the definition and documentation of project goals. 
C Necessary, but of limited value. 
D Unnecessary because project goals are defined in the proposal stage. 
E None of the above.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

3%的考友选择了A选项

71%的考友选择了B选项

3%的考友选择了C选项

23%的考友选择了D选项