A Series of non-related activities designed to accomplish single and multiple objectives. B Coordinated effort of related activities designed to accomplish a goal without a well- established end point. C Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources. D Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints. E All of the above.