The work breakdown structure (WBS) is an excellent tool for objective control and

evaluation. Which of the following is generally NOT validated through the WBS? 
A Time, schedule and cost. 
B Management coordination and organization structuring. 
C Work methods and accountability. 
D Quality of work. 
E Risk and impact decision-making.