【单选题】

The "control points" in the work breakdown structure used for isolated assignments to work 

centers are referred to as: 
A Work packages. 
B Subtasks. 
C Tasks. 
D Code of accounts. 
E Integration points.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

21%的考友选择了B选项

53%的考友选择了C选项

24%的考友选择了D选项