【单选题】

Sources for data on activity durations and resource requirements can be gathered from 

which of the following: 
A Past project records (historical data) 
B Commercial techniques (standard practices, rules of thumb) 
C Past project team members knowledge (experience, oldtimers) 
D All of the above 
E A and C only 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

17%的考友选择了A选项

6%的考友选择了B选项

2%的考友选择了C选项

75%的考友选择了D选项