You are managing an internal project where a vice president from the user group is acting 

as the sponsor. You have just been informed by your team that the critical path has slipped by 
three weeks. You should: 
A Immediately inform the sponsor and ask for advice 
B Do nothing until the slippage occurs 
C See the sponsor after you have evaluated alternatives, recommendations, and performed an 
impact analysis 
D Look for someone to blame before you see the sponsor 
E Inform your senior management of the problem and tell them that you will get back to them 
after you assessed the situation 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...