A Allocates resources to activities to find shortest schedule within fixed resource limits. B Smoothes out resource requirements by rescheduling activities within their float time. C Smooths out resource requirements by substituting activities with unassigned resources. D Attempts to reduce resource requirements within a constraint on project duration E B or D